The Nolans resource is currently at 30.3 million tonnes of measured, indicated and inferred resources, containing:
The total resources for Nolans as at November 2008 are: |
Nolans Resource Classification |
|||||
Mt |
REO% |
REO (kt) |
P2O5% |
U3O8Ib/t |
|
| Total measured | 5.1 |
3.2 |
167 |
13.5 |
0.57 |
| Total indicated | 12.3 |
2.8 |
350 |
13.4 |
0.43 |
| Total inferred | 12.8 |
2.6 |
333 |
12.2 |
0.40 |
| TOTAL | 30.3 |
2.8 |
850 |
12.9 |
0.44 |
Nolans Resource Compared |
|||
Project |
Resource |
By Products |
REO Recovery |
| Baiyunebo Inner Mongolia, China | 300Mt @ 1.5% REO |
REO a by product of iron ore separation |
~25-50% |
| Mianning, Sichuan, China | 17Mt @ 3% REO |
None |
50% |
| Mountain Pass, USA | 12Mt @ 8% REO |
None |
50-60% |
| Mt Weld, Australia | 12.24Mt @ |
None |
60% |
| Nolans, Australia | 30.3Mt @
2.8% REO |
Phosphoric Acid, Calcium Chloride, Uranium |
80-85% |
| Kangankunde Hill, Malawi | 11Mt @ 2% REO |
None |
Unknown |
![]()